Shoring Soil Retention

Combined Shoring System – Soldier Pile Wall with Tiebacks

EVstudio, contracted through Thorcon, was brought onto this project to provide shoring at a site location. One of the controlling factors of the design was to hold to a half-inch deflection limit. This deflection limit is set by a pressurized forty-two-inch pipe that would be behind the wall. The solution that we came up with […]